Milestones


 

Three-Fourths Visualisation of the new Max Planck House as generated by the architects.

October 2025

  • Start of demolition work for the expansion of the Max Planck Institute for Biological Cybernetics
  • November 18: Opening of the new Max Planck House event and visitor center
Excavator in front of a construction pit from a frog's perspective

March 2026

  • Excavation work for the two new buildings of the Max Planck Institute for Biological Cybernetics
  • Shoring work to secure the excavation pits
Workers in the shell construction laying floor slabs

October 2026

  • Start of the shell construction work for the expansion of the Max Planck Institute for Biological Cybernetics